Hormozgan Cement Company

Hormozgan Cement Company
Last Updated: November 2025
No. Project Title Brief Description Start Date End Date Progress Estimated Duration
1 Line 1 Capacity Increase Increasing clinker production capacity from 3,000 to 3,500 tons per day and boosting company revenue 2023/11/22 2026/03/19 75% 28 months
2 6 MW Solar Power Plant Providing 5% of the factory's energy needs from clean energy and fulfilling social responsibility 2023/11/22 2026/03/19 77% 28 months
3 Main Electrofilter Conversion to Baghouse Increasing filtration efficiency and removing the company from the list of polluting industries 2024/02/20 2026/03/19 31% 25 months
4 12 MW Diesel Generator Power Plant Stable electricity production by installing six 2 MW diesel generators 2025/05/05 2026/03/05 7% 10 months
5 Fuel Oil Storage Tanks Construction Increasing secondary fuel storage capacity from 11 to 22 million liters 2025/02/04 2025/12/21 71% 10 months